A federal appeals court has reinstated the lawsuit of SW Nashville EB Owner, LLC against the city of Nashville regarding a stalled building permit. The developer faced an indefinite delay on their application, purportedly linked to prospective road developments, resulting in losses exceeding $8.2 million while the property remained undeveloped. The court's decision enables the developer's claims to progress to judicial review, potentially influencing other property owners experiencing similar challenges.
US court revives Nashville developer's suit over 4-year permit freeze
The Times of India – Top Stories · By TOI WORLD DESK
Published ·
Keep reading